NWSC and systems maintenance update: power service restored to facility

July 17, 2020

All work scheduled for Thursday at the NCAR-Wyoming Supercomputing Center was completed successfully. CISL staff members and external contractors finished power infrastructure repairs and restored power to the facility at approximately 6:45 p.m. HPE and Nortek continued maintenance and repairs on Cheyenne cooling system components and the process of flushing those components. The maintenance efforts remain on schedule and the system is still expected to return to service on Saturday.